Nobody actually wants scaffolding. No one places an order for its own sake, and when the job is over nobody comes back to look at it. What is wanted is what it makes possible: that the places overhead, out of reach until now, can be stood on.
And because it comes first in the sequence, how long it takes was never only its own business.
There are only two dates on the work order: ordered on 31 March, crew and equipment on site on 1 April, and the job finished and accepted the same day.
That pace is not because scaffolding is simple. It is because scaffolding stands at the head of the sequence: until it is up, every trade behind it waits. The schedule TNO was keeping was never its own.
The compartment was tall enough to take three levels. Each was boarded out and fitted with guardrails, with ladders between them; castors underneath let the whole frame be pushed to the next working position rather than struck and built again.
None of that is refinement for its own sake. A scaffold that moves underfoot, or boards that do not sit flush, and the people on it will not commit their weight — and every trade behind them slows down with it.
The later photographs show what went on from the scaffold once it was finished — the crew on the top tier working the existing pipework at the deckhead, sparks falling away past the edge of the staging. Those are the pictures that explain why it was there at all: accepted the day it went up, and the trades behind it standing on it the next morning.
Scaffolding that has done its job is taken down and carried away, leaving nothing behind on site. What remains is what other people managed to finish in the time it held them up there.

Thirteen days from order to acceptance, with a single day on board — because it had already been assembled and tested in the workshop